Ora Banda Mining (ASX: OBM) reports that its Sand King Underground mine development tracking to plan with first ore intersected just four months after portal establishment.

Sand King forms part of the Davyhurst Gold Project in Western Australia and together with the Riverina Underground are the centrepiece of the company’s DRIVE TO 150 Project with an annual production outlook of 140,000oz to 160,000oz in FY26.

Sand King has achieved its first major milestone, intersecting multiple ore lodes in the first crosscut on the 315 Level. This is in line with internal planning and the mine remains on track to deliver first stoping ore in the March-25 Quarter. Steady state production of ~60kozpa is expected to commence in the June-25 Quarter.

Since the establishment of the Sand King portal in late August this year, mine development has advanced on schedule and in good ground conditions with 427 decline metres and a total of 835 development metres achieved to date.

Underground diamond drilling for grade control is also underway at the mine with the rig completing 5,477 metres to date of the planned 45,400 metre program. This initial program has confirmed multiple discrete high-grade lodes and additional bulk tonnage opportunities at Sand King.

The Company also recently conducted a small surface exploration drilling program at Sand King North. This 6-hole program targeted high-grade East-West ore structures and successfully infilled and extended the known lodes along strike.

“Reaching first ore at the Sand King Underground mine is exciting, especially considering that this milestone has been achieved less than 4 months after establishing the portal, and 14 months after the first drill hole targeting underground was completed,” Managing Director, Luke Creagh, said.

“The grade control and surface drilling has confirmed, enhanced and extended known mineralisation and we consider this to be at the early stages of unlocking the full potential of the Sand King mineralised system.

“As the ounce production from Sand King increases month-on-month, we are set up for a strong second half of the financial year. The combination of Riverina and Sand King high-grade ore delivers a step change to our production profile and cashflows, with a production outlook of 140,000oz to 160,000oz in FY26.”